Construction Schedule
Expected start of construction and initial site work-on or about 29 Nov 2021
Pile Installation February 24th 2022-September 21st 2022
Racking System Installation March 11th 2022-October 6th 2022
Module Installation June 27th 2022-November 4th 2022
First Circuits Energized-September 15th 2022
Commercial Operation December 31st 2022
Final Completion February 28th 2023
*Schedule subject to change due to weather and other contingencies